Howland Boulevard Construction Update

Construction began on May 1, 2007 to widen Howland Boulevard to four lanes from Elkcam Boulevard to Courtland Boulevard. The construction is scheduled to take 2.5 years with a completion date sometime in December of 2009.

The work will be done through Volusia County and Deltona Utilities. The contractor for the project is P&S Paving. The sub contractor for underground construction will be Scott Construction.

There will be 4 lanes; curb and gutter; 5’ wide sidewalks on both sides of the road; 20’ wide raised median that will be landscaped by the City of Deltona; and 6 Stormwater ponds.

Howland Boulevard will remain open to traffic at all times and every effort will be made to keep inconveniences to a minimum.

Wayne Jackson is the County Inspector on site all day. Wayne can be contacted with any questions at (386) 561-8655.

Howland Boulevard will also be widened from Courtland Boulevard